Data Source:
Ordnance Survey OpenRoad
Ordnance Survey OpenMap
Ordnance Survey OpenRivers
National Grid
BEIS
Aerial imagery
Assumption:
For woodland planting of all scales, the following physical constraints preventing woodland planting were treated as constraints:
- Buildings
- Major gas pipelines +20m buffer
- Consented and operational solar farms + 20m buffer
- Consented and operational wind farms + 50m buffer
- Water courses and bodies
For existing wind developments, it was assumed these were of notional medium scale tip height and occupied a 5 x 3 rotor diameter oval spacing, with the major axis of the oval oriented towards the prevailing wind direction, taken to be south-west (see turbine spacing below). (To mitigate impacts on the productivity of wind turbines located close to one another caused by wind turbulence, it is standard practice for developers to maintain an oval of separation between turbines that is equal to 5 times the turbine rotor diameter (the cross sectional dimension of the circle swept by the rotating blades) on the long axis, and 3 times the rotor diameter on the short axis.)
For small-medium to large sized woodland, the following additional physical constraints preventing woodland planting, were also treated as constraints:
- Roads
- Railways
- Major transmission lines +80m buffer
- Airports and airfields
- Water courses defined by linear datasets
Justification:
Physical features were excluded that prevent woodland planting.
For small-medium scale to large woodlands, an 80m buffer along major transmission lines (40m each side) was treated as a constraint to woodland planting. This acts as a safety buffer to enable falling tree clearance. National Grid do not provide rules on required buffer distances, but do provide guidance on clearance distances dependent on transmission pole and tree heights. This buffer was therefore applied using a pragmatic approach based on industry knowledge.
Small scale woodlands have the potential to be sited beneath major electricity transmission lines and therefore these were not treated as a constraint for small scale woodland planting. Further study would be required to make consideration of transmission lines operated by the local DNO National Grid (Formerly Western Power Distribution).
For all woodland scales, a 20m buffer along major gas pipelines (10m each side) was treated as a constraint to woodland planting. This acts as a safety buffer to prevent root damage to pipelines. This is in line with National Grid guidance on tree planting restrictions on pipelines. For security reasons National Grid do not provide the exact locations of the pipelines but a buffered dataset of approximately 25m in width. The 20m buffer was applied in addition to this current buffer.
It is noted that regionally operated transmission lines and additional pipelines and underground utilities may also require safety buffers to restrict planting. However, this is beyond the scope of this study and would require separate site-specific assessment.
A 20m buffer around existing and consented solar farms was treated as a constraint. This accounts for potential shading impacts on solar output.
A 50m buffer around existing and consented wind farms was treated as a constraint to account of standard practice endorsed by Natural England guidance set out in ‘TIN051’. A 50m horizontal buffer is a reasonable proxy clearance for the purposes of a strategic study given unknowns concerning tree height and turbine dimensions. A 50m buffer cannot be applied to all linear habitat features and individual trees due to a lack of data for a study of this scale.
Note: Only line data for roads was available and in order to create a footprint from the road centre, it was assumed that single carriageways are 10m in width, dual carriageways 20m and motorways 30m. In order to create a footprint from the railway centrelines data, it was assumed that railways are 15m in width. OS surface water area data includes waterways of a minimum of 2m width approximately.
OS Rivers and surface water line data are line data, and so a 1m buffer was applied to approximate a footprint of smaller waterways. In addition, many drains are included in the OS Survey OpenMap Local surface water area data that may not be a constraint to woodland planting. However,he majority of these are also covered by priority habitats, and therefore are constraints to woodland planting in this way.. Further site-specific study may therefore be required in relation to field drains when planning woodland planting.
Small sized woodlands (<5ha) including linear planting such as hedgerows with hedgerow trees have the potential to be integrated adjacent to linear physical features (such as roads, railways and water courses). In order to prevent such potentially suitable locations for this type of planting being identified, these linear datasets were not treated as constraints to small scale planting.
In addition, small sized woodlands have the potential to be integrated in the corners of airports and airfields and in conjunction with hedgerows and therefore planting in such locations may not be inappropriate.
The suitability of any scale of woodland adjacent to these types of physical features in specific locations requires detailed site-specific assessment and liaison with local stakeholders to ensure their suitability. For example, liaising with the Canal and River Trust regarding the suitability of riverside woodland to increase river shading to benefit fishing.